Skip to main content

Plastic Fabricators

How to Calculate the Required FRP Cable Tray Width for Your Cables

Correct selection of FRP cable tray width is essential for safe cable routing, heat dissipation, maintenance and any future expansions. A too narrow tray will result in crowding, whereas a too wide one would be an unnecessary cost addition.

The general rule is straightforward:

Calculate the total space taken up by the cables, add the required margin, and pick the next available standard cable tray width.

But it is necessary to consider other factors as well.

What Determines FRP Cable Tray Width?

The required width is influenced by:

  • Number of cables
  • Diameter of individual cables
  • Cable configuration
  • Required spacing between different groups of cables
  • Provision for additional future cables
  • Type of tray
  • Cable load
  • Spacing of supports

For a single layer arrangement, cable diameters serve as a good starting point in determining the required width.

Step 1: Get the Outside Diameter of Each Cable

Do not calculate tray width using the conductor size alone.

Use the overall outside diameter (OD) of the completed cable, including its insulation and outer sheath.

You can normally find the cable OD in the manufacturer’s datasheet or cable schedule.

Step 2: Calculate the Total Cable Width

For the side-by-side installation of the cables in one layer:

Width of Cables = Total of Outside Diameter

For the example illustrated above:

Power Cables: 8 × 32 = 256 mm

Control Cables: 6 × 16 = 96 mm

Cable width total:

256 mm + 96 mm = 352 mm

Thus, 352 mm is the approximate area taken up by the cables before making provision for any design clearance.

Step 3: Add Allowance for Future Cables

It is quite common for industrial cable trays to have to cater for extra cables due to plant extension or change of machinery.

Rather than fill up the tray with cables during installation, provide an appropriate spare capacity according to the project specifications.

In case of 20% planning allowance:

352 × 1.20 = 422.4 mm

Therefore, the calculation provides for a total of about 422 mm.

It would be prudent to go for the next best available standard width of the tray instead of a 422 mm width.

If a 450 mm FRP cable tray is available and meets other design specifications, it would be sensible to choose it.

Step 4: Check Cable Separation and Segregation

The sum of cable diameter does not necessarily define the width of the cable.

In some installations, there is a need for segregation between various types of cables, such as:

  • Power cables
  • Control cables
  • Instrumentation cables
  • Communication cables

The space occupied by the segregation process is also taken into account during the design of the tray.

This is especially the case for industrial facilities where the various circuit types might use the same routing system for cables.

Step 5: Check the Tray Depth

Width is not the only criterion when choosing the tray.

The depth of the tray or its side walls should also be adequate to the arrangement of cables and the carrying capacity of the producer.

Thus, Plastic Fabricators offers solid bottom FRP channel trays in the following sizes:

50 × 50 × 3 mm

100 × 50 × 3 mm

150 × 50 × 3 mm

200 × 50 × 3 mm

300 × 50 × 3 mm

450 × 50 × 3 mm

500 × 100 × 4 mm

600 × 100 × 4 mm

FRP ladder trays by Plastic Fabricators come in the widths of 300 mm, 600 mm, 700 mm, and 900 mm with the side wall height of 100 mm.

So, once the required width is calculated, it is necessary to verify whether the chosen width × depth × thickness will suit the cable load and the span of support.

Step 6: Check the Cable Weight

Even though the tray might have sufficient physical size, it may still not be suitable if the cable loading is too heavy.

To find the total weight of the cables per meter,

Total Weight of Cable per Metre = Total Weight per Metre of All Cables

Also take into account the weight of the:

  • Cables
  • Tray
  • Covers, where applicable
  • Accessories
  • Supported components, if any

The total weight will need to be compared with the capacity of the tray at the actual spacing of supports.

Technical assistance is available from Plastic Fabricators regarding FRP cable tray selection.

Worked Example: Selecting FRP Cable Tray Width

Suppose an industrial project has:

  • 8 power cables with 32 mm OD
  • 6 control cables with 16 mm OD
  • 20% allowance for future cables

Calculation

Power cable space:

8 × 32 = 256 mm

Control cable space:

6 × 16 = 96 mm

Total:

256 + 96 = 352 mm

Add 20% allowance:

352 × 1.20 = 422.4 mm

 

Tray Selection

The calculated requirement is approximately 422 mm.

The next suitable standard width could therefore be:

450 mm FRP Cable Tray

The final selection should still be checked for load capacity, support span, cable arrangement, segregation and tray depth before the purchase order is released.

Should You Choose a 300 mm, 450 mm or 600 mm FRP Cable Tray?

Cable Requirement Possible Tray Width
Small cable bundle 100–200 mm
Medium cable bundle 300 mm
Larger single-layer bundle 450 mm
Large cable grouping 500–600 mm
Large power cable routes 600–900 mm ladder tray

These are preliminary selection ranges, not universal design rules. The final width must come from the cable schedule, installation arrangement and applicable project requirements.

Plastic Fabricators offer FRP cable trays from 50 mm to 900 mm wide, depending on the tray type.

FRP Cable Tray Width vs Cable Tray Fill

One must be cautious about not confusing the tray width with a universal “fill percentage.”

There are various standards and design codes that approach cable layout, fill percentages, spacing, thermal performance, and load differently. IEC 61537 mostly deals with the requirements and tests concerning cable tray and ladder systems and must not be mistaken for a universal cable fill percentage.

For this reason, it is better to rely on the governing electrical code and cable manufacturer’s information to determine the proper fill percentage.

When Should You Choose an FRP Ladder Tray Instead?

It is also not enough that the number of cables is used alone to determine the type of tray.

For example, the ladder type FRP cable tray can work best for large cables since the air can flow around the cables, which makes them easily accessible for inspection and for adding more cables later. The plastic fabricators use their ladder trays for power distribution and larger cables, while the channel trays for instrument and control cables.

Select the tray based on:

Type of cable + heat generated + protection required + installation + load

Common Mistakes When Calculating FRP Cable Tray Width

The use of wire size rather than cable OD

Always use the full cable’s OD.

Overloading of tray to its physical maximum capacity

Reserve sufficient capacity in accordance with the project design rather than overloading the tray.

Disregard of cable segregation

There are differences in routing of power, instrumentation, and communication cables.

Looking at width and not the load

A wide tray does not necessarily mean a strong tray.

Neglecting the need for expansion

Expansions often take place in industrial installations, so it needs to be taken into consideration in the design phase.

Choosing the tray first and then the cable schedule

Cable schedule comes first, then the tray width should follow the cable requirement.

FRP Cable Tray Width Calculation Formula

For a basic single-layer calculation:

Required Width ≈ OD of all Cables + Separation Distance + Provision for Future Capacity

Where:

OD of all Cables = ∑(Number of Cables × OD of Cable)

In the case of the solved problem:

Required Width ≈ (8 × 32 + 6 × 16) × 1.20

Required Width ≈ 422.4 mm

Choose the next appropriate size of tray and confirm the load capacity, span, depth, separation etc.

What Information Should You Give an FRP Cable Tray Manufacturer?

For an exact quote and technical recommendation, please provide:

  • Cable schedule
  • Quantity of cables
  • Outside diameter of cables
  • Weights of cables
  • Required length of tray run
  • Classification of power, control, or instrumentation
  • Required segregation
  • Span of supports
  • Environment of installation
  • Required type of tray
  • Drawing or route drawing

Plastic Fabricators will also accommodate any special cutting, drilling, notching and other fabrication needs.

Final Takeaway

The calculation of the correct FRP cable tray size depends on the cable schedule you have, not the tray catalog.

Find out the total outer diameter of your cables, the needed space between them, and choose the most suitable standard tray size. Then, check the tray depth, the loading, cable segregation and installation requirements.

To get a personalized FRP cable tray suggestion, provide your cable schedule, cable diameters, routing distance, span and application specifics to the manufacturer.

How to choose the right FRP cable tray size? Send your cable schedule to Plastic Fabricators and we’ll suggest the correct FRP cable tray size and quote the price.